High Voltage ProjectBlue Power Karuizawa 7th Solar Power PlantSold after completion

6-5 Toriyamae, Kosaka, Saku City, Nagano, Japan.

Estimated annual amount of
electricity generated

About 0,000 kWh/year

Equivalent to the annual power consumption of
about 219 common households.

*Supposing that the power consumption of a common household is 300 kWh/month

Estimated annual amount of
CO2 reduced

About 0 t-CO2/year

The same effect as the planting of
about 20,000 cedar trees.

*Calculated under the assumption that the CO2 absorption amount per 50-year-old cedar tree is about 14 kg

Outline of the project
Site area 14,050.00 ㎡(Equivalent to roughly 0.30 Tokyo Domes)
Generation capacity 580.80 kW
Estimated annual amount of electricity generated 791,790.12 kWh/year
Estimated annual amount of CO2 reduced 414.90 t-CO2/year
Foundation Placeable foundation Pile foundation
Module S-Energy Co.,LTD. 300 W × 1,936 modules
Power conditioner HUAWEI TECHNOLOGIES CO.LTD. 33.30 kW × 14 units
Cubicle Kansai Denki Kogyo Co., Ltd.
Construction Started in 06,2018
Status Started operation in 01,2019