Special High Voltage ProjectTentative name:Taihaku CC Solar Power PlantIn preparation
75-3 Makainyama, Nagafukuro, Akiumachi, Taihaku-ku, Sendai City, Miyagi, Japan, and other.
Estimated annual amount of
electricity generated
About 0,0,000 kWh/year
Equivalent to the annual power consumption of
about 17,567 common households.
*Supposing that the power consumption of a common household is 300 kWh/month
Estimated annual amount of
CO2 reduced
About 0,0 t-CO2/year
The same effect as the planting of
about 2,360,000 cedar trees.
*Calculated under the assumption that the CO2 absorption amount per 50-year-old cedar tree is about 14 kg
Outline of the project | |
---|---|
Site area | 1,184,950.80 ㎡(Equivalent to roughly 25.34 Tokyo Domes) |
Generation capacity | 51,065.03 kW |
Estimated annual amount of electricity generated | 63,241,224.89 kWh/year |
Estimated annual amount of CO2 reduced | 33,138.40 t-CO2/year |
Foundation | Being selected |
Module | Being selected |
Power conditioner | Being selected |
Cubicle | Being selected |
Construction | In preparation |
Status | To be operated in 2025 |